DOW-UAP-D112 is modification P00001 to AAWSAP contract HHM402-08-C-0072, issued by the Defense Intelligence Agency's Virginia Contracting Activity at Bolling Air Force Base, Building 6000, Washington, D.C., effective September 2, 2009. The Department of War released it in PURSUE Release 06 on September 18, 2026, as part of the contract chain running from DOW-UAP-D110 through DOW-UAP-D116.123
Parties and Authority
The modification amends the September 22, 2008 base contract (DOW-UAP-D111) with Bigelow Aerospace Advanced Space Studies, LLC, addressed at 1899 W. Brooks Ave., North Las Vegas, Nevada. Executed as a supplemental agreement under FAR 52.217-9, Option to Extend the Term of the Contract (March 2000), it carries both a modification amount and an obligated amount of $0.00. The contracting officer's name is withheld.3
Purpose of the Modification
The modification extends the base period of performance to September 30, 2009, revises Option Year 1 dates to October 1, 2009, through September 30, 2010, and exercises Option Year 1 subject to the availability of funds. Citing FAR 52.232-18 (April 1984), it stipulates that funds are not presently available and that no government payment liability arises until funds become available to the Contracting Officer and the contractor receives written notice. All other terms and conditions remain unchanged.3
Option Year Schedule ($25,000,000.00)
The six Option Year 1 line items total $25,000,000.00: Monthly Status Reports ($3,241,200.00), Project Management Plan for Tasks 3.a.1 through 3.a.12 ($9,957,600.00), Research Report for Tasks 3.a.1 through 3.a.12 ($6,006,000.00), Comprehensive Integrated Threat Assessment ($460,800.00), Travel ($115,000.00), and Other Direct Costs ($5,219,400.00), each marked as an option. The schedule dates these items September 22, 2009, through September 21, 2010, which does not match the October 1, 2009, to September 30, 2010 term this modification sets.3 That original $25,000,000.00 ceiling explains why the subsequent $11,948,810.00 obligation in modification P00002 (DOW-UAP-D113) constituted a funding reduction of more than 52 percent.3
The file establishes that Virginia Contracting Activity exercised Option Year 1 of HHM402-08-C-0072 on September 2, 2009, at a $25,000,000.00 scheduled price subject to future funding availability, before P00002 (DOW-UAP-D113) later obligated reduced funding. It does not describe research results or aerial phenomena.3